Case study · North West

32-Storey Tower Façade Clean

A new build-to-rent tower needed quarterly façade cleaning. Cradle access was unreliable and disrupted residents.

The problem

A new build-to-rent tower needed quarterly façade cleaning. Cradle access was unreliable and disrupted residents.

Our method

Two pairs of rope technicians worked a planned drop sequence over 5 days, using pure-water systems for glazing and biocide for stained cladding panels.

The outcome

Zero resident complaints. Programme now runs on a rolling 90-day cycle with a fixed-price contract.

IRATA-trained rope access technicians carrying out 32-storey tower façade clean in the North West
Representative image — project photography for this job is available on request.